Example Lead Paint Projects in Cedar Park

Each example follows a lead job from the first question to the finished work: the house, what was tested, what the work involves, how long it takes and roughly what it would cost. About 95 in every 100 Cedar Park homes were built after 1978 and are outside lead paint rules, so these examples are about the older houses, and most of them start with a test.

Lead test before new windows in a 1940s house

Example project

Old wood window sash and sill with white paint flaking to bare wood and a cracked pane
Home
1940s single-story house in Cedar Park, about 1,400 sq ft, one of the few that old in town
Original request
Replace the original wood windows
Surfaces
Window sashes, sills and trim, doors and exterior trim
Existing finish
Layers of white paint, flaking to bare wood on the sills; one cracked pane
Testing
Lead inspection of the whole house, with a written report
Timeline
One visit of about three hours; report within a week
Cost
$575

Scope of work

A walk-through of every painted surface inside and out, a reading on each type of window part, door and trim, and a written report listing which surfaces have lead paint and which do not. The new windows are not part of this price.

Project overview

In this example, the owners want new windows in a house built in the 1940s, one of the few Cedar Park homes that old. The original sashes are flaking, and they want to know whether the window company has to work lead-safe before they sign anything.

A whole-house inspection answers that for every painted surface at once. Here the report finds lead paint on the window sills and the exterior trim and none on the interior walls, so lead-safe work is planned for the windows and the exterior trim, and left out of the interior repaint the owners have in mind for later.

The goal

The goal is a clear list of which windows and trim need lead-safe work, so the window quote is right and the inside walls carry no extra cost.

Process

  1. Before the visit We check the build year and ask which rooms and windows the project will touch.
  2. Visit Readings on each painted surface type, room by room, plus the doors and exterior trim.
  3. Within a week A written report listing the surfaces with lead paint and those without.
  4. Afterwards The report goes to the window installer, so their quote covers lead-safe work on the right surfaces only.

Planning right

  • In a house built before 1978, replacing windows always falls under EPA lead-safe rules, however small the job, unless a test shows the paint is lead-free.
  • Keep the report. It covers later projects too, such as painting or a kitchen remodel.
  • Do not sand or scrape a flaking sill to see what is under it. Test first.
  • Built in 1978 or later? Then the rules do not apply and no test is needed.

Get a free quoteMore about lead inspections and risk assessments

Risk assessment before buying an older house

Example project

Older wood house with turned porch posts, green siding and a window sash with peeling white paint
Home
Wood house in Leander built before 1940, with a front porch
Original request
Know about lead before closing on the purchase
Surfaces
Porch posts, window sashes and trim, siding, and the floors and sills inside
Condition
Paint peeling on the porch posts and a front window
Testing
Risk assessment with paint readings, dust wipes and soil samples
Timeline
Visit and report inside the 10-day period the purchase contract allows for a lead check
Cost
$950

Scope of work

Paint readings on the peeling and worn surfaces, dust-wipe samples from floors and window sills, soil samples along the walls and from bare patches of the yard, lab fees, and a written report of the hazards found with ways to fix each one.

Project overview

In this example, buyers are under contract on one of the few Leander houses built before 1940. The seller knows of no lead reports, and the paint on the porch posts and a front window is peeling.

For a purchase, a risk assessment fits better than a full inspection. It looks for hazards as they are now, such as peeling paint, lead dust on sills and lead in the soil by the walls, and gives the buyers a list of fixes to price or negotiate before the inspection period ends.

The goal

The goal is a report in hand before the deadline, so the buyers know which hazards exist, what fixing them involves and whether the price should change.

Process

  1. Day one Purchase contract signed with the lead inspection period in place.
  2. Day two Site visit with paint readings on the peeling surfaces, dust wipes from floors and sills and soil samples along the walls.
  3. By day eight Lab results and a written report listing each hazard and ways to fix it.
  4. Before the period ends The buyers use the report to ask for repairs or a price change, or to walk away.

Planning right

  • Book the visit as soon as the contract is signed. Lab results take several days and the period is short.
  • Ask the seller for any old lead reports. They have to hand over what they have.
  • Soil along the walls often holds more lead than the open yard, because old paint has fallen there for years.
  • Peeling paint on porch railings and low trim is where small children are most likely to pick up lead.

Get a free quoteMore about lead inspections and risk assessments

Dust cleanup after trim sanding in a 1960s house

Example project

Empty room with bare wood floors, two bags of used plastic sheeting and a small vacuum after cleanup
Home
1960s single-story house in Cedar Park
Original request
Make a bedroom safe after the trim was sanded
Room
One bedroom with wood floors, two windows and a half-glass door
What happened
Window and door trim scraped and sanded for a repaint; a paint test then found lead
Work
HEPA vacuuming, wet wiping and dust-wipe tests
Timeline
One day of cleaning; lab results two to five working days later
Cost
$950

Scope of work

The room closed off, plastic and debris bagged, HEPA vacuuming of floors, sills and trim, wet wiping of every surface twice, a second HEPA pass, and dust-wipe samples from the floor and window sills sent to a lab. If a sample fails, that area is cleaned and tested again.

Project overview

In this example, the owner scraped and sanded the window and door trim in a bedroom before repainting it, then learned the house was built in the 1960s. A paint test on the trim came back positive for lead, and a grandchild is due to stay in the room.

Sweeping and an ordinary vacuum spread fine lead dust instead of removing it, so the room is cleaned with HEPA vacuums and wet wiping, then dust-wipe samples go to a lab. The room is ready only when the results come back under the limits.

The goal

The goal is a bedroom with lab results showing the lead dust is gone, so the family can use it again without guessing.

Process

  1. First The door kept shut and the room left alone, with no sweeping or ordinary vacuuming.
  2. Cleaning day Plastic and debris bagged, HEPA vacuuming top to bottom, wet wiping twice, then a second HEPA pass.
  3. Next day Dust-wipe samples from the floor and the window sills, taken by a separate tester.
  4. Two to five days later Lab results. If one fails, that area is cleaned again and retested.

Planning right

  • Test the paint before sanding trim in any house built before 1978. Wet scraping makes far less dust than dry sanding.
  • An ordinary vacuum blows fine lead dust back into the air. A HEPA vacuum holds it.
  • Window sills collect the most dust, so they are the samples most likely to fail.
  • Keep children out of the room until the results are back.

Get a free quoteMore about lead dust cleanup and clearance testing

Sealing old painted door trim in a 1940s house

Example project

Doorway with flaking green paint on the casing and baseboard, plastic sheeting on the floor and a HEPA vacuum
Home
1940s single-story house in Cedar Park
Original request
Stop the old trim paint flaking without stripping the trim
Testing
Lead paint in the older layers on the door casings and baseboards
Surfaces
Casings, baseboards, the door and the walls around them in one room
Area
About 300 sq ft sealed
Finish
Two coats of encapsulant, then paint to match
Timeline
Three working days, after a patch test
Cost
$2,200

Scope of work

Plastic on the floor, loose paint misted and hand-scraped off, HEPA vacuuming and wet wiping, a patch test of the encapsulant on one casing, two coats over the trim, door and walls, paint to match and a final clean. The old paint stays under the coating.

Project overview

In this example, the casings and baseboards in a 1940s house carry layers of old green paint that are flaking at the edges, and a test shows lead in the older layers. The owners like the original trim and do not want it stripped or replaced.

Encapsulation suits paint that is still mostly stuck down. The loose flakes are scraped off wet, the surface is cleaned, and a coating made for sealing lead paint is brushed on and painted. It keeps the trim and costs less than stripping, but the lead paint is still there, so it has to be kept in good condition and written down for future work.

The goal

The goal is original trim with a smooth, sound finish and no flaking paint, and a written record of where the lead paint is sealed in.

Process

  1. Before work A small patch of encapsulant on one casing, checked once it cures to make sure it holds to the old paint.
  2. Day one Floor covered, loose paint misted and scraped off by hand, debris bagged.
  3. Day two HEPA vacuuming and wet wiping, then the first coat of encapsulant.
  4. Day three Second coat, paint to match, a final clean and the plastic taken up.

Planning right

  • Encapsulation only works over paint that is still stuck down. Where paint is peeling across a whole surface, removal or covering is the better choice.
  • Rubbing surfaces wear through a coating. Door edges and stops may need a different fix than the casings.
  • Keep a note of what was sealed and where. Anyone sanding or cutting the trim later needs to know the lead paint is there.
  • Look at the coating once a year and touch up any chips.

Get a free quoteMore about lead paint encapsulation and enclosure

Peeling exterior trim on an older house

Example project

Green wood siding, a white porch post and railing and a wood front door, with paint peeling on a window sill
Home
Single-story 1960s house from Lakeway’s first years, with a covered front porch
Original request
Repaint the outside, where the white trim is peeling
Testing
Lead paint on the window sills and trim, porch posts and railing; none on the green siding
Surfaces
Window sills and trim, porch posts and railing, fascia and eaves, plus the siding
Work
Wet scraping, sanding with HEPA-fitted tools, primer and two coats
Timeline
Six to eight working days, avoiding wind and the hottest afternoons
Cost
$8,600

Scope of work

Plastic sheeting on the ground around the house and over plants, windows and doors closed, loose paint on the lead-painted trim scraped off wet, edges sanded with tools fitted to HEPA vacuums, chips picked up daily, a primer and two coats on the trim, and the siding cleaned and painted to match. Rotten sill wood would be extra.

Project overview

In this example, the owners of a 1960s house from Lakeway’s first years plan to repaint the outside, and the white trim is peeling to bare wood on the window sills. Because the house was built before 1978, the trim, siding, posts and railing are tested first. Lead paint shows up on the trim, posts and railing, but not on the green siding.

That changes how the trim is prepared, not whether it gets painted. Paint chips land on plastic instead of in the beds, nothing is power-washed or dry-sanded, and work stops on windy days. The siding is prepared and painted the usual way.

The goal

The goal is sound, freshly painted trim and siding, with the old lead paint chips cleaned up rather than left in the soil.

Process

  1. Before work Lead test on the trim, siding, posts and railing, and a check for soft wood under the sills.
  2. Day one Plastic laid around the house and plants covered; windows and doors closed.
  3. Days two to four Trim, posts and railing scraped wet and sanded with HEPA-fitted tools; chips picked up every evening.
  4. Days five to seven Primer and two coats on the trim; siding cleaned and painted.
  5. Last day Plastic folded inward and bagged, the ground checked for chips, and a walk-round.

Planning right

  • Power washing lead paint sprays chips across the yard. The trim is scraped wet by hand instead.
  • Heat and wind both matter. Work runs in the mornings and stops when wind would carry dust.
  • Soft, gray wood under a sill will not hold paint. Plan for repair if a screwdriver sinks in.
  • Vegetable beds near the house are worth a soil test if old paint has been falling for years.

Get a free quoteMore about exterior lead paint removal

Lead-safe kitchen remodel in a 1970s house

Example project

Floor plan, folder, sealed sample containers and a tape measure on a desk beside a painted window
Home
1970s two-story house in Cedar Park
Original request
Open up the kitchen and replace the cabinets and window
Testing
Lead paint on the kitchen window and door trim; none on the walls
Work area
Kitchen, about 180 sq ft, and the doorway to the dining room
Lead-safe add-on
Plastic sheeting, HEPA cleanup, a cleaning check and disposal
Timeline
Adds one to two days to a three-week remodel
Estimated add-on cost
$2,300

Scope of work

Plastic over the floor and across the doorways, the kitchen closed off from the rest of the house, window and door trim taken out in whole pieces rather than scraped, HEPA vacuuming and wet wiping each day, a final cleaning check and bagged disposal. Cabinets, counters, plumbing and the new window are priced in the remodel itself.

Project overview

In this example, the owners are remodeling the kitchen of a house built in the 1970s. A lead test before the design is final shows lead paint on the window and door trim, but not on the walls.

That narrows the lead-safe work to the parts of the job that disturb the trim: taking out the window and removing the door casing. The rest of the remodel goes ahead as usual, and the lead-safe work is an add-on to the remodeling price, not a separate project.

The goal

The goal is a finished kitchen with no lead dust left behind, and a lead-safe add-on priced only for the surfaces that need it.

Process

  1. Before work Test report reviewed and the work area marked on the floor plan.
  2. Day one Kitchen closed off with plastic, floor covered, warning signs up.
  3. Demolition days Trim and window misted and removed in whole pieces, bagged each day; HEPA vacuuming every evening.
  4. Last dusty day Every surface in the work area cleaned, then the cleaning check before the plastic comes down.
  5. Then The remodel carries on as usual.

Planning right

  • Test before the design is final. If the trim is lead-free, the add-on may not be needed at all.
  • Taking trim off in whole pieces makes far less dust than scraping or sanding it in place.
  • Keep children and pets out of the work area until the cleaning check is done.
  • Ask the remodeler whether the lead-safe work is in their price or quoted on top.

Get a free quoteMore about lead-safe remodeling

Request a free lead paint removal quote

Tell us roughly when the house was built, which rooms or surfaces the work would touch and where the property is. We'll get back to you soon with an estimate or any questions we have. Estimates are free and there's no obligation.

Call (737) 520-3701

Call (737) 520-3701